Drax Group (LON: DRX), the UK power generator, said 2026 adjusted EBITDA will be significantly above the £721m analyst consensus, and its shares rose 6.1% in early trading today. EBITDA is core earnings before interest, tax, depreciation and one-offs. The company also set longer-term targets at its capital markets day.
Drax traded at 872p in a delayed quote from 8.42 am, up from Friday’s close of 821.5p. The shares opened at 860.5p after the 7 am announcement. They remain below the 2026 high of about 937.5p, reached in February.
The company gave no new 2026 figure. The £721m consensus, the average analyst forecast, was compiled by Drax as of 17 November and sat in a range of £710m to £736m.
Drax said it had added about £50m to its 2026 contracted power position, after strong performance in September and October from system support and generation. The Balancing Mechanism, the grid operator’s market for real-time power balancing, added to the benefit. Expectations depend on continued good operational performance.
The capital markets day targets are adjusted EBITDA of £800m to £900m in 2029, covering existing business and committed projects, and more than £1bn in 2031, which includes new investment. The 2029 midpoint of £850m is about 18% above the 2026 consensus. Drax says that implies EBITDA growth above 12% a year on average over 2027 to 2031, with dividend per share growing by more than 10% a year.
The mix has to change to get there. Biomass Operations produced over 80% of 2025 EBITDA, but Drax expects solar, wind and flexible generation such as batteries and gas peakers to be the majority by 2029. Funding comes from more than £3bn of free cash flow over 2026 to 2031 and a higher leverage target of 2.5x net debt to EBITDA, up from about 2x.

Will Gardiner, Drax’s chief executive, framed the shift as a change in earnings quality:
The Group is broadening its generation portfolio, resulting in higher earnings quality supported by an integrated trading and optimisation platform designed to capture more value from every megawatt.
Will Gardiner, Chief Executive, Drax Group
Open items remain. The data-centre project with Brookfield’s Radiant platform at Drax Power Station has no tenant and needs planning and regulatory approvals. The buyback stays paused, with about £0.8bn due to be returned to shareholders over 2026 to 2031. The capital markets day webcast starts at 2pm today.